What Buildertrend's reports can and cannot tell an owner
Buildertrend holds most of what a building firm needs to know about its jobs, and its records are accurate. The trouble starts when a number leaves the screen for a spreadsheet or a meeting without its definition.
Here are three cases from a reporting build for a residential design-build firm. In each one the record was right and the obvious reading of it was wrong.
A job budget has three costs, not one
On one remodel, the budget screen showed three figures side by side: a projected cost in the hundreds of thousands, a committed cost of roughly a ninth of that, and an actual cost of a few hundred dollars. All three were correct.
They answer different questions. Committed cost is what has been ordered through approved purchase orders, plus time-clock shifts not yet approved. Actual cost is what has been billed or approved. Projected cost is the forecast, and by default it takes the highest of the revised budget, the committed cost and the actual cost.
Someone copying job cost into a spreadsheet could pick any of the three and tell a very different story. Before a cost goes on a dashboard, name which one it is.
A closed warranty claim does not tell you which visit fixed it
We opened one claim that had two appointments a week apart. A staff member had marked both complete on the same later date. Across that snapshot, only about one in five closed claims had a recorded closure date.
So you can count closed claims with confidence. Repair time and first-visit fix rate need more evidence, which means appointments being completed in the system as the visits happen.
An average depends on when the clock starts
Across nearly two thousand selection items on about a hundred jobs, it took about 23 days from opening an item to recording all of the client's choices.
Calling that "clients take 23 days to decide" would charge the builder's preparation time to the customer. To answer that question, you need the date the choices were actually sent to the client.
What to take from this
- Counts and totals in Buildertrend can be trusted once you know which figure you are reading.
- Durations and rates depend on dates being entered when things happen, not afterwards.
- Write the definition beside every number before it leaves the system.
Reference: Buildertrend's Job Costing Budget overview (opens in a new tab)