The weekly numbers a design-build owner should see

Goodluck Ogundare ·

Owners usually ask me for more numbers than anyone will read. On one build the first list had 83. A long list is useful as a register, but nobody runs a firm from 83 numbers.

Here is the short set I would put in front of an owner every week, grouped by the question each one answers.

Are we selling enough?

  • New leads this week, and where they came from.
  • Leads that became a signed design agreement or contract.
  • Days from first contact to signature.
  • Value of signed work this month against the same month last year.

These come from the CRM. They only work if every lead is entered, including the ones that arrive by phone.

Is work moving?

  • Jobs in each stage, from design through pre-construction to site.
  • Days each job has sat in its current stage.
  • Jobs that have not moved in 30 days.
  • Jobs due to start in the next four weeks.

The stages come from the project board and Buildertrend. Counting jobs tells you little. How long each one waits between hand-offs tells you where the firm is stuck.

Are we making money on the jobs?

  • Budget against actual cost for each open job.
  • Change orders approved and not yet billed.
  • Invoiced and not yet collected.
  • Gross margin on jobs closed this quarter.

These need Buildertrend and the accounting package to agree on jobs and cost codes. Budget against actual depends on a budget being entered for every job. If it is not, start there.

What needs a decision this week?

One short list of exceptions: stalled jobs, jobs over budget, overdue invoices. Do not rank it. The owner decides what matters.

Rules that keep the numbers useful

  • One definition per number, written down and agreed. If sales and production count a start differently, settle it before it goes on a screen.
  • Show coverage. If a number is based on 40 of 55 jobs, say so beside it.
  • Set targets from where you are today, then move them. A target nobody is near gets ignored.
  • Keep the weekly view to one screen. Everything else belongs on a detail page.

You can build this view in a spreadsheet to begin with. It becomes a system when the numbers have to come from three or four tools at once and update without anyone copying them.